Achievements Of JNNSM

GOVERNMENT OF INDIA

MINISTRY OF  NEW AND RENEWABLE ENERGY

RAJYA SABHA

UNSTARRED QUESTION NO-1353

ANSWERED ON-26.03.2012




(a) whether Government has fixed any target for generation of solar power under the Jawaharlal Nehru National Solar Mission (JNNSM) during the last three years;

(b) if so, the details thereof;

(c) the achievements made during the last three years, State-wise;

(d) whether the targets have been achieved; and
(e) if not, the reasons therefor?

ANSWER

THE MINISTER OF NEW AND RENEWABLE ENERGY
(DR. FAROOQ ABDULLAH)

(a): No, Sir. Targets have been fixed for First Phase of JNNSM (2010-13).

(b): Details are attached as Annexure ‘A’.
(c): The State-wise achievements made during the Phase-I of Mission are attached as Annexure ‘B’.
(d): The targets of Phase-I of JNNSM are to be met by 2013.
(e) Does not arise.

Twitter Link To This Post
Facebook Link To This Post

Google + Link To This Post

YS Chowdary Facebook
YS Chowdary Twitter
YS Chowdary Blog
YS Chowdary Wikipedia


Monday, November 28, 2011

Village Energy Security Projects

GOVERNMENT OF INDIA

MINISTRY OF  NEW AND RENEWABLE ENERGY

RAJYA SABHA

QUESTION NO  96

ANSWERED ON  28.11.2011



Will the Minister of NEW AND RENEWABLE ENERGY be pleased to satate :-
(a) whether Government has identified villages/ hamlets for test projects on village energy security throughout the country;

(b) if so, the details thereof, state-wise; and

(c) the details of the test projects undertaken in unelectrified remote villages and hamlets, during the last three years?
   
ANSWER
     
THE MINISTER OF NEW AND RENEWABLE ENERGY
(DR. FAROOQ ABDULLAH)

(a), (b)&(c): A Statement is laid on the Table of the House.

Statement
Statement in reply to parts (a), (b) & (c) of Rajya Sabha Starred Question No. 96 for 28.11.2011

(a)&(b): Yes Sir. The Ministry has identified 79 villages/ hamlets for implementation of test projects in 10 States of the country. The State-wise number of test projects identified/ under implementation, are given at Annexure - I.

(c): During the last three years, 20 test projects, of which 17 test projects during 2008-09 and 03 test projects during 2009-10 were undertaken in un-electrified remote villages and hamlets by the Ministry. The location-wise list of test projects under taken in un-electrified remote villages and hamlets is given at Annexure – II. During 2010-11, no test projects have been undertaken, as in the Mid-Term Appraisal of the 11th Five Year Plan carried out by the Planning Commission in September, 2009, ‘it was decided to concentrate on consolidating the projects already taken up for implementation’. It was also decided that no new test projects will be supported.



YS Chowdary Facebook
YS Chowdary Twitter
YS Chowdary Blog
YS Chowdary Wikipedia
Showing posts with label Farooq. Show all posts
Showing posts with label Farooq. Show all posts

Monday, March 26, 2012

Achievements Of JNNSM

GOVERNMENT OF INDIA

MINISTRY OF  NEW AND RENEWABLE ENERGY

RAJYA SABHA

UNSTARRED QUESTION NO-1353

ANSWERED ON-26.03.2012




(a) whether Government has fixed any target for generation of solar power under the Jawaharlal Nehru National Solar Mission (JNNSM) during the last three years;

(b) if so, the details thereof;

(c) the achievements made during the last three years, State-wise;

(d) whether the targets have been achieved; and
(e) if not, the reasons therefor?

ANSWER

THE MINISTER OF NEW AND RENEWABLE ENERGY
(DR. FAROOQ ABDULLAH)

(a): No, Sir. Targets have been fixed for First Phase of JNNSM (2010-13).

(b): Details are attached as Annexure ‘A’.
(c): The State-wise achievements made during the Phase-I of Mission are attached as Annexure ‘B’.
(d): The targets of Phase-I of JNNSM are to be met by 2013.
(e) Does not arise.

Twitter Link To This Post
Facebook Link To This Post

Google + Link To This Post

YS Chowdary Facebook
YS Chowdary Twitter
YS Chowdary Blog
YS Chowdary Wikipedia


Monday, November 28, 2011

Village Energy Security Projects

GOVERNMENT OF INDIA

MINISTRY OF  NEW AND RENEWABLE ENERGY

RAJYA SABHA

QUESTION NO  96

ANSWERED ON  28.11.2011



Will the Minister of NEW AND RENEWABLE ENERGY be pleased to satate :-
(a) whether Government has identified villages/ hamlets for test projects on village energy security throughout the country;

(b) if so, the details thereof, state-wise; and

(c) the details of the test projects undertaken in unelectrified remote villages and hamlets, during the last three years?
   
ANSWER
     
THE MINISTER OF NEW AND RENEWABLE ENERGY
(DR. FAROOQ ABDULLAH)

(a), (b)&(c): A Statement is laid on the Table of the House.

Statement
Statement in reply to parts (a), (b) & (c) of Rajya Sabha Starred Question No. 96 for 28.11.2011

(a)&(b): Yes Sir. The Ministry has identified 79 villages/ hamlets for implementation of test projects in 10 States of the country. The State-wise number of test projects identified/ under implementation, are given at Annexure - I.

(c): During the last three years, 20 test projects, of which 17 test projects during 2008-09 and 03 test projects during 2009-10 were undertaken in un-electrified remote villages and hamlets by the Ministry. The location-wise list of test projects under taken in un-electrified remote villages and hamlets is given at Annexure – II. During 2010-11, no test projects have been undertaken, as in the Mid-Term Appraisal of the 11th Five Year Plan carried out by the Planning Commission in September, 2009, ‘it was decided to concentrate on consolidating the projects already taken up for implementation’. It was also decided that no new test projects will be supported.